As Level Projects times
Unless otherwise stated the deadline is 10:30 Hours

Week Beginning Week Deadline

A 13-Nov-06

Week 1 Briefing and project work starts in earnest
Project proposals submitted Wednesday 15th

B 20-Nov-06

Week 2

A 27-Nov-06

Week 3 Project Specification complete Tuesday 28th

B 4-Dec-06

Week 4

A 11-Dec-06

Week 5 First view of Implementation Tuesday 12th

B 18-Dec-06

W eek 6 Implementation Complete Tuesday 19th All work in Excel stops!

25-Dec-06

Week 7

1-Jan-07

Week 8

A 8-Jan-07

Week 9 User Guide submitted Tuesday 9th

B 15-Jan-07

W eek 10 Testing submitted Tuesday 16th

A 22-Jan-07

Week 11

B 29-Jan-07

Week 12 Implementation Write-up submitted Tuesday 30th

A 5-Feb-07

W eek 13 Evaluation Submitted Tuesday 6th

B 12-Feb-07

Wee k 14

A 19-Feb-07

Week 15 HALF TERM

B 26-Feb-07

Week 16 Reports bound and complete Tuesday 27th

A 5-Mar-07

Week 17
Student Declaration.   I acknowledge the receipt of the above instructions on..............
I realize that failure to meet any of the above deadlines will result in disciplinary action being taken, as each deadline represents several weeks’ work.
I understand that I must meet the final deadline in order that the project is marked prior to being sent to the examiners.
I understand there will be no deadline extensions.
Signed......................................................... ...................
   