Gantt Chart
Tutorial Exercises
Exercise
Kate McLean is intending to have a party for her son's
7th birthday. The sequence of activities that need to be undertaken is
as follows:
| Task |
Antecedent |
Description |
Time (hours) |
| A |
None |
Decide on date for party |
1 |
| B |
A |
Book bouncy castle |
1 |
| C |
A |
Send invitations |
4 |
| D |
C |
Receive replies |
7 |
| E |
D |
Buy toys and balloons |
1 |
| F |
D |
Buy food |
3 |
| G |
E |
Blow up balloons |
2 |
| H |
F |
Make food |
1 |
| I |
H, G |
Decorate room |
1 |
| J |
B |
Get bouncy castle |
1 |
| K |
J, I |
Have party |
1 |
| L |
K |
Clear up |
4 |
| M |
K |
Send back bouncy castle |
1 |
| N |
L |
Send out thank-you letters |
3 |
| O |
M |
Give unwanted gifts to OXFAM |
3 |
Draw a Gantt (Bar) Chart for the project. Mark a review
stage at 14 hours. Illustrate that tasks A, B, C, D and G have been
completed. State which tasks are ahead and which tasks are behind
schedule and any anomolies you may identify.
|