Gantt Chart Tutorial Exercises

Exercise

Kate McLean is intending to have a party for her son's 7th birthday. The sequence of activities that need to be undertaken is as follows:

 

Task Antecedent Description Time (hours)
A None Decide on date for party 1
B A Book bouncy castle 1
C A Send invitations 4
D C Receive replies 7
E D Buy toys and balloons 1
F D Buy food 3
G E Blow up balloons 2
H F Make food 1
I H, G Decorate room 1
J B Get bouncy castle 1
K J, I Have party 1
L K Clear up 4
M K Send back bouncy castle 1
N L Send out thank-you letters 3
O M Give unwanted gifts to OXFAM 3

Draw a Gantt (Bar) Chart for the project. Mark a review stage at 14 hours. Illustrate that tasks A, B, C, D and G have been completed. State which tasks are ahead and which tasks are behind schedule and any anomolies you may identify.

   